autodesk-domain-verification=V-MLXGxgpCO4m1piu5Ue

Contact Us

Use the form on the right to contact us.

You can edit the text in this area, and change where the contact form on the right submits to, by entering edit mode using the modes on the bottom right. 

362 E 10th Ave
Vancouver, BC, V5T 4G5

604.558.1123

Lanefab design build is an award winning residential design and construction company based in Vancouver BC. We craft single family homes, duplexes, and lane houses with a focus on modern design and environmental efficiency.

Construction Process

Lanefab's Construction Process

1. Cost & Contract

2. Demolition, Excavation & Servicing

3. Foundations

4. Framing & Windows

5. Plumbing and Electrical Rough-In

6. Drywall

7. Millwork and Finishes

8. Completion Items

9. Post-Occupancy Checkup 


1. Cost and Contract

  • After all of the design work has been completed, and building permits have been issued, we will put together a final cost for all of the work described in the 'contract documents' which include the drawings, the specifications, and the list of allowances.

    >> Read more about construction costs here
     
  • 'Allowances' are dollar amounts that are allocated to specific items within the total cost of the project (i.e. $8/sf for tile).  
     
  • For new construction we'll typically put together a 'Fixed Cost' contract. For renovations we'll usually do a 'Cost Plus' contract, where the actual costs, plus a margin, are invoiced every two weeks.
     
  • We can generally start construction within 3 weeks of signing a contract.

2. Demolition, Excavation & Servicing

  • Hazmat:
    If there is an existing house to be demolished, then we may need to start off with testing for hazardous materials, including asbestos. If hazardous materials are found, there will be costs incurred to remove the material before demolition starts.
     
  • Deconstruction:
    Where possible we will opt for 'deconstruction' vs. 'demolition' so that building materials and fixtures can be reclaimed and re-used elsewhere.
     
  • Demolition:
    This typically involves having an excavator smash the existing building, and then separating the metal, wood and concrete.
  • Excavation & Servicing:
    'Servicing' means putting in the necessary underground services including sewer, water, gas and electrical.  For the sewer work this often involves a large trench running through the property, along with large piles of dirt that will be used later for backfill.  

    The excavation will typically be deep enough to remove all of the organic top soil so that the building can sit on solid ground.  

    In some cases we'll encounter large boulders, oil tanks, or areas of boggy soil that will require extra time and cost to address.
Separate sanitary and storm water sewer pipes connecting a laneway house to the city services in the front yard.

Separate sanitary and storm water sewer pipes connecting a laneway house to the city services in the front yard.


3. Foundations

  • Footings and Forms:
    After excavating and putting down a layer of gravel, we'll use plywood to form up the concrete foundations.
     
  • Damp-proofing:
    After the concrete has hardened, the forms are removed and we typically add a damp-proofing coating to the outside of the concrete, along with a drainage board which keeps water from building up against the concrete.
     
  • Drain Tile:
    A perforated pipe is installed next to the bottom of the foundation walls. This 'drain tile' allows ground water to be collected and drained away so as to keep the foundation and basement dry.
Foundation forms being filled with concrete.

Foundation forms being filled with concrete.


4. Framing and Windows

  • Prefab Panels:
    On many of our projects we'll use prefab Structural Insulated Panels (SIPs) for the walls and roof.  These panels are cut to shape off site, but are then delivered and installed on to the foundation.   We'll often use timber framing (like the reclaimed beams shown here) in combination with the prefab panels.
An in-swing 'tilt-n-turn' window by Euroline. Here it is centre mounted, with outward facing strap anchors.

An in-swing 'tilt-n-turn' window by Euroline. Here it is centre mounted, with outward facing strap anchors.

SIP wall panels supporting reclaimed timber beams.

SIP wall panels supporting reclaimed timber beams.

Windows and Doors:
For most of our projects we use a 'centre mount' window detail where the window is mounted into the centre of the thick wall. This provides better energy performance, weather tightness, and a unique look.


5. Plumbing and Electrical Rough-In

  • Service Wall:
    Most of our projects employ a double wall system where there is a structural outer wall, and a non-structural service wall on the inside that holds all of the plumbing, ductwork, and sprinkler piping.
     
  • Plumbing & Ventilation Rough-In:
    At this point in the project we'll install the main drainage piping that runs under the floor and up the walls.  We'll also run cold and hot water lines to each plumbing fixture in the house. In Vancouver, where fire sprinklering is required, we'll install all of the sprinkler piping at this stage.
     
  • Electrical Rough-In:
    At this point we'll run wiring to all of the plugs, lights and switches in the house. We'll also run cables for TV, internet, security and automation.
     
  • Service Wall Insulation:
    After all of the plumbing, ductwork and wires are installed we'll put an additional layer of insulation into the service wall. This might be batt insulation, mineral wool or spray foam.
Service wall filled with 2lb spray foam at the Tsawassen passive house.

Service wall filled with 2lb spray foam at the Tsawassen passive house.

Drainage pipes for a bathroom. The inner 'service wall' will be framed around these pipes.

Drainage pipes for a bathroom. The inner 'service wall' will be framed around these pipes.

Installing radiant-floor heating pipes prior to the ground floor concrete slab being poured.

Installing radiant-floor heating pipes prior to the ground floor concrete slab being poured.

 

6. Drywall and Painting

  • Boarding:
    The gypsum wall board (drywall) is installed in large sheets ~4'x8' or larger, and holes are cut for light fixtures and plugs.
     
  • Mudding:
    After the house is boarded, a layer of drywall mud is applied to all of the joints and corners. After it dries, the mud can be sanded to a smooth finish making the joints invisible.  

    This process of mudding and sanding can take a full week due to the time required to dry out the mud in between passes.
     
  • Painting:
    After the drywall is sanded smooth, the painters will apply a coat of primer and then several coats of the finish paint colour.
     
Mudding the joints at the 11th and Carnarvon lane house.

Mudding the joints at the 11th and Carnarvon lane house.


7. Millwork and Finishes

  • Exterior Finishes:
A thin veneer of real stone being applied to the exterior of a lane house.

A thin veneer of real stone being applied to the exterior of a lane house.


8. Completion Items


9. Post Occupancy Checkup

Remodeling and Home Design